Xcel Energy – Vale, Colorado

- Owner – Xcel Energy
 - October – November 2011
 - Two Directional Drills with a combined Footage of 3450′
 - Pilot Drill, Ream and Pull 16″ High Pressure Gas Line
 - Brought in to complete original bore that was unsuccessfully attempted by drilling contractor
 - Crews worked 12 hour rotating shifts around the clock until initial bore completion.
 - Owner Requested Brotherton to complete a second additional bore